Sl.No e-Published Date Bid Submission Closing Date Tender Opening Date Title/Ref.No./Tender Id Organisation Name Corrigendum
481. 09-Oct-2025 01:00 PM 04-Feb-2026 11:00 AM 05-Feb-2026 11:30 AM 4 laning of NH 167 from Gudebellur at Design Km 182.930 to Mahabubnagar at Design Km 262.940 of Hyderabad Panaji section (Length 80.01km) under NH(O) on Hybrid Annuity Mode (HAM) in the state of Telangana/NHAI/Tech/TS /NH 167/2024/E72619/2025_NHAI_251709_1 National Highways Authority of India icon image
482. 09-Oct-2025 09:00 AM 20-Jan-2026 03:00 PM 21-Jan-2026 03:30 PM Development, Operation and Maintenance of the Multi Modal Logistics Park (MMLP) Nagpur at Sindi, in Wardha District in the State of Maharashtra through Public Private Partnership on Design, Build, Finance, Operate and Transfer (DBFOT) basis/MMPL/MMLP/Nagpur/Conc./2025/2025_NHAI_251673_1 National Highways Authority of India icon image
483. 06-Oct-2025 01:00 PM 20-Jan-2026 03:00 PM 22-Jan-2026 11:00 AM Widening and strengthening to 2-Lane with Paved Shoulder of NH-322 Musrigharari to Darbhanga (Km 72.05 to Km 96.00) in the state of Bihar on EPC Mode for the year 2025-26 Job No. NH-322/BHR/2025-26/132 (Including Utility Shifting)./03/NH/Samastipur/EPC/2025-26/2025_MoRTH_880199_1 Ministry of Road Transport and Highways icon image
484. 04-Oct-2025 06:58 PM 12-Jan-2026 12:00 PM 12-Jan-2026 12:00 PM RFP for Construction of Viaducts, ROR/RFO, Major Bridges, Minor Bridges, Animal Underpass, Animal Overpass, ROB, RUB/LHS, Earthwork, Blanketing, Buildings etc and other associated works for construction of new Double Line track for DFCC loading from Ch.157.920 to Ch.184 (except tunnels) in Koderma Detour section in Sonnagar-Andal 3rd and 4th line project on EPC Mode in Dhanbad Division of East Central Railway./ECR-CAO-C-S-EPC-02-25-26/84713967 Ministry of Railways --
485. 03-Oct-2025 05:00 PM 09-Feb-2026 03:00 PM 10-Feb-2026 03:00 PM Construction of Maski Bypass Starts at existing Km 144.220 and ends at existing Km 151.760 and Sindhanur Bypass Starts at existing Km 168.370 and ends at existing Km 180.800 on NH 150A in the State of Karnataka/RW/ BNG /NH-150A/Maski Sindhanur Bypass/62/2023( 2nd Call)/2025_MoRTH_880046_1 Ministry of Road Transport and Highways icon image
486. 01-Oct-2025 06:00 PM 04-Feb-2026 11:00 AM 05-Feb-2026 11:30 AM 4-laning of Armoor - Jagtial - Mancherial Section of NH-63 from Jagtial (design km. 92.700) to Mancherial (design km. 160.995) total length 68.295 on Hybrid Annuity Mode (HAM)/NHAI/Tech/ TS/2024/239275/2025_NHAI_251031_1 National Highways Authority of India icon image
487. 01-Oct-2025 06:00 PM 04-Feb-2026 11:00 AM 05-Feb-2026 11:30 AM 4-Laning of Jagtial Karimnagar Section of NH-563 from Design Ch.0.000 km (Existing chainage 90/500 on NH-63) to Design Ch. 58.866 km (near SH1 Ch. 170.400 km) at Karimnagar Bypass End (Design Length 58.866 km) on BOT (Toll) mode./NHAI/Tech /TS/2024/239275/2025_NHAI_251035_1 National Highways Authority of India icon image
488. 01-Oct-2025 05:30 PM 04-Feb-2026 11:00 AM 05-Feb-2026 11:30 AM 4-laning of Armoor - Jagtial - Mancherial Section of NH-63 from Armoor (design km. 29.100) to Jagtial (design km. 92.700) (total length 63.300 km) on Hybrid Annuity Mode (HAM)/NHAI/Tech /TS/2024/239275/2025_NHAI_251026_1 National Highways Authority of India icon image
489. 29-Sep-2025 05:00 PM 15-Jan-2026 05:00 PM 16-Jan-2026 11:00 AM Rehabilitation and upgradation of Ghoti to Trimbak section of NH-160A (km 53.500 to km 101.100) to 4-LPS (47.600 km) in the State of Maharashtra on EPC Mode/12014/148/2024-MAH/ZONE-IV-I/2025_MoRTH_879574_1 Ministry of Road Transport and Highways icon image
490. 29-Sep-2025 05:00 PM 15-Jan-2026 05:00 PM 16-Jan-2026 11:00 AM Rehabilitation and upgradation of Trimbak - Mokhada - Jawhar - Manor - Palghar section of NH-160A to 2-lane/4-lane with paved shoulder (107.035 km) in the State of Maharashtra on EPC Mode./12014/148/2024-MAH/ZONE-IV-II/2025_MoRTH_879578_1 Ministry of Road Transport and Highways icon image